For a fabrication with several fillet welds of different sizes and lengths, how much weld metal, arc time and cost does it take, and does it fit my quoted price?

Cost estimate of all the fillet welds on a weldment: for each weld run the weld metal per metre from the leg size and excess, then arc time from the deposition rate, paid time from the operating factor, and labour, filler and shielding gas costs (as the weld cost tool, run by run), summed with any fit-up and handling time, against the price you have quoted for the welding.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Number of weld runsrunsHow many different weld runs (sizes) to include.
Weld run 1
Fillet legmmFillet leg size of weld run 1.
Total lengthmTotal length of weld run 1 on the weldment.
Weld run 2
Fillet legmmFillet leg size of weld run 2.
Total lengthmTotal length of weld run 2.
Weld run 3
Fillet legmmFillet leg size of weld run 3.
Total lengthmTotal length of weld run 3.
Weld run 4
Fillet legmmFillet leg size of weld run 4.
Total lengthmTotal length of weld run 4.
Process and rates
Excess weld metal (convexity, spatter)%Allowance for convexity and spatter over the plain triangle.
Weld metal densityg/cm³Density of the weld metal (7.85 for steel).
Deposition ratekg/hWeld metal deposited per hour of arc time.
Operating factor (arc-on share of paid time)%Share of paid time the arc is on.
Filler deposition efficiency%Share of the filler bought that ends up in the weld.
Labour and overhead rate$/hLabour and overhead per paid hour.
Filler price$/kgPrice of filler wire or rod.
Shielding gas flowL/minShielding gas flow while the arc is on (0 for self-shielded processes).
Gas price$/m³Price of shielding gas.
Fit-up and handling timehTime for fit-up, tacking, turning and handling, charged at the labour rate.
Price quoted for the welding$The price allowed for the welding.

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Number of weld runs
Illustration: Number of weld runsA row of identical items being counted; Number of weld runs is how many there are.nExample: 3 runsNumber of weld runs
What it is
How many separate fillet weld sizes the weldment has. Each run is one leg size with its total length; runs beyond this count are ignored even if they hold values.
Units and format
Enter a number in runs: runs. The form accepts 1 runs to 4 runs. Use a whole number. Required: the tool does not calculate until every input is valid.
Example
The form opens with 3 runs as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Group all welds of the same leg size into one run and add their lengths together.

Weld run 1

What this means: Fillet leg
Illustration: Fillet legA bar with a dimension line and arrows from one end to the other, marking the length Fillet leg.zExample: 6 mmFillet leg
What it is
The leg size of the first group of fillet welds: the length of each side of the weld triangle measured along the joined faces.
Units and format
Enter a number in mm: millimetres. The form accepts 0.000001 mm to 50 mm. Required: the tool does not calculate until every input is valid.
Example
The form opens with 6 mm as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal, arc time and cost per metre all rise with the square of the leg.
Get it right
Use leg length, not throat thickness; the throat of an equal-leg fillet is smaller than the leg.
What this means: Total length
Illustration: Total lengthA bar with a dimension line and arrows from one end to the other, marking the length Total length.LExample: 2.4 mTotal length
What it is
The total length of all welds of the first leg size on the weldment, adding every separate weld of that size.
Units and format
Enter a number in m: metres. The form accepts 0 m to 10000 m. Required: the tool does not calculate until every input is valid.
Example
The form opens with 2.4 m as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Every cost of this run rises in direct proportion to its length.
Get it right
Enter the length in metres; a weld measured as 600 mm is 0.6 m.

Weld run 2

What this means: Fillet leg
Illustration: Fillet legA bar with a dimension line and arrows from one end to the other, marking the length Fillet leg.zExample: 8 mmFillet leg
What it is
The leg size of the second group of fillet welds: the length of each side of the weld triangle measured along the joined faces.
Units and format
Enter a number in mm: millimetres. The form accepts 0.000001 mm to 50 mm. Required: the tool does not calculate until every input is valid.
Example
The form opens with 8 mm as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal, arc time and cost per metre all rise with the square of the leg.
Get it right
Use leg length, not throat thickness; the throat of an equal-leg fillet is smaller than the leg.
What this means: Total length
Illustration: Total lengthA bar with a dimension line and arrows from one end to the other, marking the length Total length.LExample: 1.2 mTotal length
What it is
The total length of all welds of the second leg size on the weldment, adding every separate weld of that size.
Units and format
Enter a number in m: metres. The form accepts 0 m to 10000 m. Required: the tool does not calculate until every input is valid.
Example
The form opens with 1.2 m as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Every cost of this run rises in direct proportion to its length.
Get it right
Enter the length in metres; a weld measured as 600 mm is 0.6 m.

Weld run 3

What this means: Fillet leg
Illustration: Fillet legA bar with a dimension line and arrows from one end to the other, marking the length Fillet leg.zExample: 5 mmFillet leg
What it is
The leg size of the third group of fillet welds: the length of each side of the weld triangle measured along the joined faces.
Units and format
Enter a number in mm: millimetres. The form accepts 0.000001 mm to 50 mm. Required: the tool does not calculate until every input is valid.
Example
The form opens with 5 mm as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal, arc time and cost per metre all rise with the square of the leg.
Get it right
Use leg length, not throat thickness; the throat of an equal-leg fillet is smaller than the leg.
What this means: Total length
Illustration: Total lengthA bar with a dimension line and arrows from one end to the other, marking the length Total length.LExample: 3 mTotal length
What it is
The total length of all welds of the third leg size on the weldment, adding every separate weld of that size.
Units and format
Enter a number in m: metres. The form accepts 0 m to 10000 m. Required: the tool does not calculate until every input is valid.
Example
The form opens with 3 m as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Every cost of this run rises in direct proportion to its length.
Get it right
Enter the length in metres; a weld measured as 600 mm is 0.6 m.

Weld run 4

What this means: Fillet leg
Illustration: Fillet legA bar with a dimension line and arrows from one end to the other, marking the length Fillet leg.zExample: 10 mmFillet leg
What it is
The leg size of the fourth group of fillet welds: the length of each side of the weld triangle measured along the joined faces.
Units and format
Enter a number in mm: millimetres. The form accepts 0.000001 mm to 50 mm. Required: the tool does not calculate until every input is valid.
Example
The form opens with 10 mm as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal, arc time and cost per metre all rise with the square of the leg.
Get it right
Use leg length, not throat thickness; the throat of an equal-leg fillet is smaller than the leg.
What this means: Total length
Illustration: Total lengthA bar with a dimension line and arrows from one end to the other, marking the length Total length.LExample: 0.5 mTotal length
What it is
The total length of all welds of the fourth leg size on the weldment, adding every separate weld of that size.
Units and format
Enter a number in m: metres. The form accepts 0 m to 10000 m. Required: the tool does not calculate until every input is valid.
Example
The form opens with 0.5 m as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Every cost of this run rises in direct proportion to its length.
Get it right
Enter the length in metres; a weld measured as 600 mm is 0.6 m.

Process and rates

What this means: Excess weld metal (convexity, spatter)
Illustration: Excess weld metal (convexity, spatter)A bar of 100 parts with the share marked; Excess weld metal (convexity, spatter) is that share out of 100. The bar follows the value you type.0 %100 %Example: 15%Excess weld metal (convexity, spatter)
What it is
Extra weld metal over the plain triangular fillet section, allowing for a convex face, reinforcement and spatter. It is added to the theoretical weld metal of every run.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 0% to 100%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 15% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal, arc time, labour, filler and gas all rise in proportion to one plus this share.
Get it right
Type the percentage itself, not a fraction; it is a share of the plain triangular section.
What this means: Weld metal density
Illustration: Weld metal densityA cube of material: density Weld metal density is its mass divided by the volume it fills.massvolumeρExample: 7.85 g/cm³Weld metal density
What it is
The density of the deposited weld metal, used to turn the weld cross-section into a mass per metre. Take it from the filler supplier or the parent metal data.
Units and format
Enter a number in g/cm³: grams per cubic centimetre (1 g/cm³ = 1000 kg/m³). The form accepts 0.000001 g/cm³ to 25 g/cm³. Required: the tool does not calculate until every input is valid.
Example
The form opens with 7.85 g/cm³ as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Weld metal mass, and so every time and cost, rises in proportion to density.
Get it right
Enter it in g/cm³; a value in kg/m³ must be divided by 1000.
What this means: Deposition rate
Illustration: Deposition rateItems moving past a point on a conveyor; Deposition rate is how many pass in each unit of time.count pointDExample: 3 kg/hDeposition rate
What it is
The mass of weld metal the process lays down per hour while the arc is actually burning, from the process or consumable supplier for your wire size and settings.
Units and format
Enter a number in kg/h: kg/h. The form accepts 0.000001 kg/h to 50 kg/h. Required: the tool does not calculate until every input is valid.
Example
The form opens with 3 kg/h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
A higher deposition rate cuts arc time, paid time, labour and gas cost in inverse proportion.
Get it right
Use the deposition rate for arc-on time, not an output per shift that already includes stoppages; stoppages are covered by the operating factor.
What this means: Operating factor (arc-on share of paid time)
Illustration: Operating factor (arc-on share of paid time)A bar of 100 parts with the share marked; Operating factor (arc-on share of paid time) is that share out of 100. The bar follows the value you type.0 %100 %Example: 30%Operating factor (arc-on share of paid time)
What it is
The share of the welder’s paid time during which the arc is on; the rest goes on changing wire, chipping, repositioning and similar tasks. Arc time is divided by it to get paid welding time.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 1% to 100%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 30% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
A lower operating factor raises paid welding time and labour cost in inverse proportion.
Get it right
Type the percentage itself. Fit-up and handling time is entered separately below, so do not allow for it twice here.
What this means: Filler deposition efficiency
Illustration: Filler deposition efficiencyInput on the left and useful output on the right with the loss split off; Filler deposition efficiency is output divided by input.inputuseful outputlossηExample: 92%Filler deposition efficiency
What it is
The share of the filler wire or rod you buy that ends up in the weld, after losses to spatter, stub ends and slag. The weld metal mass is divided by it to get the filler purchased.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 1% to 100%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 92% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
A lower efficiency raises filler cost only; labour and gas are not affected.
Get it right
Type the percentage itself. Take the figure for your process and consumable from the supplier.
What this means: Labour and overhead rate
Illustration: Labour and overhead rateA price tag on one unit of measure; Labour and overhead rate is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $95/hLabour and overhead rate
What it is
The cost of one paid hour of welding labour including overheads, as charged by your organisation. It is applied to paid welding time and to fit-up and handling time.
Units and format
Enter a number in $/h: money per hour. The form accepts $0/h to $10000/h. Required: the tool does not calculate until every input is valid.
Example
The form opens with $95/h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Labour and fit-up cost rise in direct proportion to the rate.
Get it right
Use the fully burdened rate your finance team uses for quoting, not the welder’s wage alone.
What this means: Filler price
Illustration: Filler priceA price tag on one unit of measure; Filler price is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $6/kgFiller price
What it is
The price you pay per kilogram of filler wire, rod or electrode, from your supplier invoice or quotation.
Units and format
Enter a number in $/kg: money per kilogram. The form accepts $0/kg to $1000/kg. Required: the tool does not calculate until every input is valid.
Example
The form opens with $6/kg as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Filler cost rises in direct proportion to the price.
Get it right
Use the price per kilogram, not per spool or per packet.
What this means: Shielding gas flow
Illustration: Shielding gas flowA pipe with liquid or gas moving through it; Shielding gas flow is the volume that passes per unit of time.QExample: 15 L/minShielding gas flow
What it is
The flow of shielding gas through the torch while the arc is on, read from the flowmeter or the welding procedure. Gas used is this flow times arc time.
Units and format
Enter a number in L/min: litres per minute. The form accepts 0 L/min to 100 L/min. Required: the tool does not calculate until every input is valid.
Example
The form opens with 15 L/min as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Gas cost rises in direct proportion to the flow.
Get it right
Use 0 for self-shielded or flux processes with no gas. Gas used between welds is not counted.
What this means: Gas price
Illustration: Gas priceA price tag on one unit of measure; Gas price is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $12/m³Gas price
What it is
The cost of one cubic metre of shielding gas as delivered, from your gas supplier, including any cylinder rental you want to recover.
Units and format
Enter a number in $/m³: money per m³. The form accepts $0/m³ to $1000/m³. Required: the tool does not calculate until every input is valid.
Example
The form opens with $12/m³ as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Gas cost rises in direct proportion to the price.
Get it right
Gas is often priced per cylinder; divide the cylinder price by its contents in cubic metres.
What this means: Fit-up and handling time
Illustration: Fit-up and handling timeA timeline from a start mark to an end mark; Fit-up and handling time is the time between them.startendtExample: 1.5 hFit-up and handling time
What it is
The paid time for the whole weldment spent on fit-up, tacking, turning, cleaning and handling, outside the weld runs themselves. It is charged at the labour rate.
Units and format
Enter a number in h: hours. The form accepts 0 h to 10000 h. Required: the tool does not calculate until every input is valid.
Example
The form opens with 1.5 h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each hour adds one hour of the labour rate to the total.
Get it right
Enter it in hours for the whole weldment; 45 minutes is 0.75 h.
What this means: Price quoted for the welding
Illustration: Price quoted for the weldingA stack of coins and a note representing the money amount Price quoted for the welding.$Example: $300Price quoted for the welding
What it is
The price you have quoted or been allowed for the welding work on this weldment. The estimated total cost is compared with it.
Units and format
Enter a number in $: an amount of money; use one currency for every money input. The form accepts $0 or more. Required: the tool does not calculate until every input is valid.
Example
The form opens with $300 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Compare like with like: if the quote also covers material or finishing, use only the welding share.

Method and formulas

  1. Weld metal per metre = ½ leg² × (1 + excess) × density; arc time = mass ÷ deposition rate; paid time = arc time ÷ operating factor (as the weld cost tool).
  2. Labour = paid time × rate; filler = mass ÷ efficiency × price; gas = arc minutes × flow × gas price.
  3. Each run multiplied by its length; fit-up time at the labour rate added.
  4. Example: 1.0752 kg of weld metal, 2.6946 h paid including fit-up, $267 in all.

Limitations

  • Fillet welds only; groove welds have a different cross-section.
  • Deposition rate and operating factor vary widely with process, position and shop.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Price the welding on a frame or bracket
  • Compare leg sizes on cost
  • Check a welding quote

Who it is for

  • Estimators
  • Fabrication engineers
  • Welding supervisors

What you get

  • Weld metal, arc and paid time by run
  • Labour, filler and gas cost
  • Total against the quote

Interpreting the result

  • Weld metal grows with the square of the leg: one size up on a long run usually costs more than all the short runs.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 1438–1441. Topic reference; no source tables or recommended settings are reproduced.

BIZOMAT tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.

Open the Weldment Cost Estimate (Weld Metal, Arc Time, Labour, Filler and Gas by Run) calculator