Electroplating Plan (Time, Current, Loads and Cost per Part)

How long must this load plate to reach the thickness, can the rectifier supply the current, how many loads does the batch take, and what does it cost per part?

Plan of a rack or barrel electroplating job: deposition rate and time to thickness by Faraday’s law with cathode efficiency (as the electroplating thickness tool), total current for the load against the rectifier capacity and current density against your window, loads for the batch and total hours with handling time, metal deposited, electrical energy, and cost per part from metal, energy and labour.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
DepositchoiceMetal deposited and its valence in the bath.
Current densityA/dm²Cathode current density.
Cathode efficiency%Share of current that deposits metal (cathode efficiency).
Thickness wantedµmAverage thickness wanted.
Area per partdm²Plated area of one part.
Parts per loadParts on one rack or in one barrel load.
Parts in the batchParts to plate.
Rectifier capacityALargest current of the rectifier.
Lowest current density for good depositsA/dm²Low end of the current-density window for the bath (your value).
Highest current density for good depositsA/dm²High end of the window (your value).
Tank voltageVVoltage across the tank at this current.
Handling time per loadminTime to load, rinse and unload each load.
Electricity price$/kWhPrice of electricity.
Anode metal price$/kgPrice of the anode metal per kilogram.
Labour and overhead rate$/hLabour and overhead per hour of line time.

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Deposit
Illustration: DepositThe options for Deposit, with the one currently selected highlighted.Nickel (Ni²⁺)Copper, acid (Cu²⁺)Copper, cyanide (Cu⁺)Zinc (Zn²⁺)+4 moreExample: Nickel (Ni²⁺)Deposit
What it is
The metal being deposited and the bath type, which fixes the atomic mass, valence and density used in Faraday’s law.
Units and format
Choose one of 8 options from the list: Nickel (Ni²⁺); Copper, acid (Cu²⁺); Copper, cyanide (Cu⁺); Zinc (Zn²⁺); Chromium, hexavalent (Cr⁶⁺); Tin, acid (Sn²⁺); Silver (Ag⁺); Gold, cyanide (Au⁺).
Example
The form opens with “Nickel (Ni²⁺)” selected as a worked example. Choose the option that matches your case.
Get it right
Copper from cyanide and acid baths deposits at different valences, so pick the bath you actually run.
What this means: Current density
Illustration: Current densityA simple circuit with a supply and a load; Current density is one of its electrical quantities.~loadJExample: 4 A/dm²Current density
What it is
The cathode current density: the plating current per unit of plated area on the parts. It sets the deposition rate and, with the area, the current per load.
Units and format
Enter a number in A/dm²: amperes per square decimetre. The form accepts 0.000001 A/dm² to 100 A/dm². Required: the tool does not calculate until every input is valid.
Example
The form opens with 4 A/dm² as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Doubling it halves the plating time and doubles the current per load.
Get it right
Use the area actually plated, not the projected area, when relating current to density.
What this means: Cathode efficiency
Illustration: Cathode efficiencyInput on the left and useful output on the right with the loss split off; Cathode efficiency is output divided by input.inputuseful outputlossηExample: 95%Cathode efficiency
What it is
The cathode efficiency of the bath: the share of the current that deposits metal rather than producing hydrogen. Take it from the bath supplier or your process records.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 1% to 100%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 95% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Plating time is inversely proportional to efficiency.
Get it right
Type the percentage itself, for example 95, not 0.95.
What this means: Thickness wanted
Illustration: Thickness wantedThe cross-section of a plate or wall with a dimension across its thickness, marking Thickness wanted.ssection through the materialExample: 20 µmThickness wanted
What it is
The average deposit thickness wanted on the plated surface, from the drawing or plating specification.
Units and format
Enter a number in µm: micrometres (µm, microns). The form accepts 0.000001 µm to 2000 µm. Required: the tool does not calculate until every input is valid.
Example
The form opens with 20 µm as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Plating time and metal used rise in proportion.
Get it right
This is an average; recesses plate thinner and edges thicker, so measure on the significant surface.
What this means: Area per part
Illustration: Area per partA shaded shape whose enclosed surface is the area Area per part.AenclosedsurfaceExample: 0.5 dm²Area per part
What it is
The surface area of one part that receives the deposit, including both sides and edges that are wetted and plated.
Units and format
Enter a number in dm²: dm². The form accepts 0.000001 dm² to 10000 dm². Required: the tool does not calculate until every input is valid.
Example
The form opens with 0.5 dm² as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Current per load and metal used are proportional to it.
Get it right
Use square decimetres: 1 dm² = 100 cm² = 0.01 m².
What this means: Parts per load
Illustration: Parts per loadA row of identical items being counted; Parts per load is how many there are.nExample: 40Parts per load
What it is
The number of parts on one rack or in one barrel load plated together at the same time.
Units and format
Enter a plain number with no unit. The form accepts 1 to 100000. Use a whole number. Required: the tool does not calculate until every input is valid.
Example
The form opens with 40 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
More parts per load raise current per load and reduce the number of loads.
What this means: Parts in the batch
Illustration: Parts in the batchA row of identical items being counted; Parts in the batch is how many there are.nExample: 1000Parts in the batch
What it is
The total number of parts to plate in this job. It sets the number of loads and the cost per part.
Units and format
Enter a plain number with no unit. The form accepts 1 to 100000000. Use a whole number. Required: the tool does not calculate until every input is valid.
Example
The form opens with 1000 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
The last load is counted as a full load even if it is part-filled.
What this means: Rectifier capacity
Illustration: Rectifier capacityA simple circuit with a supply and a load; Rectifier capacity is one of its electrical quantities.~loadI maxExample: 100 ARectifier capacity
What it is
The largest current the rectifier feeding this tank can deliver. The current per load is checked against it.
Units and format
Enter a number in A: amperes. The form accepts 0.000001 A to 1000000 A. Required: the tool does not calculate until every input is valid.
Example
The form opens with 100 A as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Use the rated continuous output, not a short-term peak.
What this means: Lowest current density for good deposits
Illustration: Lowest current density for good depositsA simple circuit with a supply and a load; Lowest current density for good deposits is one of its electrical quantities.~loadJ minExample: 2 A/dm²Lowest current density for good deposits
What it is
The lowest current density at which this bath still gives a sound deposit, from the bath supplier’s data or your trials.
Units and format
Enter a number in A/dm²: amperes per square decimetre. The form accepts 0 A/dm² to 100 A/dm². Required: the tool does not calculate until every input is valid.
Example
The form opens with 2 A/dm² as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Highest current density for good deposits
Illustration: Highest current density for good depositsA simple circuit with a supply and a load; Highest current density for good deposits is one of its electrical quantities.~loadJ maxExample: 6 A/dm²Highest current density for good deposits
What it is
The highest current density at which this bath still gives a sound deposit without burning, from the bath supplier’s data or your trials.
Units and format
Enter a number in A/dm²: amperes per square decimetre. The form accepts 0.1 A/dm² to 100 A/dm². Required: the tool does not calculate until every input is valid.
Example
The form opens with 6 A/dm² as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
It must be above the lowest value, or the tool stops.
What this means: Tank voltage
Illustration: Tank voltageA simple circuit with a supply and a load; Tank voltage is one of its electrical quantities.~loadVExample: 6 VTank voltage
What it is
The voltage across the tank, anode to cathode, while plating at this current. It is used only for the electrical energy.
Units and format
Enter a number in V: volts. The form accepts 0.000001 V to 100 V. Required: the tool does not calculate until every input is valid.
Example
The form opens with 6 V as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Energy and its cost rise in proportion.
Get it right
Read it on the rectifier meter during plating, not the open-circuit value.
What this means: Handling time per load
Illustration: Handling time per loadA timeline from a start mark to an end mark; Handling time per load is the time between them.startendtExample: 10 minHandling time per load
What it is
The time each load spends out of plating: racking, cleaning, rinsing and unloading. It adds to the plating time to give line hours.
Units and format
Enter a number in min: minutes. The form accepts 0 min to 600 min. Required: the tool does not calculate until every input is valid.
Example
The form opens with 10 min as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Enter minutes per load, not per part.
What this means: Electricity price
Illustration: Electricity priceA price tag on one unit of measure; Electricity price is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $0.25/kWhElectricity price
What it is
What you pay for one kilowatt-hour of electricity, including usage charges, from your power bill or contract.
Units and format
Enter a number in $/kWh: money per kilowatt-hour. The form accepts $0/kWh to $10/kWh. Required: the tool does not calculate until every input is valid.
Example
The form opens with $0.25/kWh as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Anode metal price
Illustration: Anode metal priceA price tag on one unit of measure; Anode metal price is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $20/kgAnode metal price
What it is
The price of the anode metal, or the metal salts that replace it, per kilogram of metal deposited. Take it from your supplier.
Units and format
Enter a number in $/kg: money per kilogram. The form accepts $0/kg to $1000000/kg. Required: the tool does not calculate until every input is valid.
Example
The form opens with $20/kg as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Price per kilogram of metal, not per anode bar or per litre of solution.
What this means: Labour and overhead rate
Illustration: Labour and overhead rateA price tag on one unit of measure; Labour and overhead rate is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $60/hLabour and overhead rate
What it is
The cost of one hour of line time: operator labour plus the overhead your costing method assigns to the plating line.
Units and format
Enter a number in $/h: money per hour. The form accepts $0/h to $10000/h. Required: the tool does not calculate until every input is valid.
Example
The form opens with $60/h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Use a rate per line hour, since the tool multiplies by total line hours.

Method and formulas

  1. Mass rate per area = J × efficiency × atomic mass ÷ (valence × 96 485); rate = mass rate ÷ density; time = thickness ÷ rate (as the electroplating thickness tool).
  2. Current = J × area per part × parts per load.
  3. Loads = batch ÷ parts per load (rounded up); hours = loads × (time + handling) ÷ 60.
  4. Cost per part = (metal × price + V I t × price of energy + hours × rate) ÷ batch.
  5. Example: 20 µm takes 25.691 min at 80 A per load; the batch needs 25 loads and costs about 0.91137 per part.

Limitations

  • Average thickness; edges plate thicker and recesses thinner.
  • Costs exclude chemicals, waste treatment and rework.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Quote a plating job
  • Check whether a rectifier can run a bigger load
  • Estimate metal and power used per part

Who it is for

  • Platers
  • Estimators
  • Process engineers

What you get

  • Deposition rate, time and current per load
  • Loads, hours and metal for the batch
  • Energy and cost per part

Interpreting the result

  • If the rectifier limits the load, fewer parts per rack at the same current density keep quality and time.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 1467, 1500–1516. Topic reference; no source tables or recommended settings are reproduced.
  • Atomic masses: IUPAC Commission on Isotopic Abundances and Atomic Weights — https://ciaaw.org

BIZOMAT tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.

Open the Electroplating Plan (Time, Current, Loads and Cost per Part) calculator