Learning-Curve Quote (Batch Hours, Cost and Price per Unit)

With the learning curve, how many hours will this batch take, what does each unit cost, and does the price I am offered give my margin?

Quote for a batch where labour time falls with repetition: time for the first and last unit, cumulative and average hours on the unit learning curve (as the learning curve tool), set-up, labour and machine cost at your hourly rate, material per unit, overhead, total and unit cost, the price per unit for your margin, and the margin the offered price gives.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Hours for the first unithHours the first unit takes (estimate or prototype record).
Learning rate%Learning rate: each doubling of quantity multiplies the unit time by this (80–90% typical for manual assembly).
Units in the batchUnits in the batch.
Set-up hourshSet-up hours for the batch.
Labour and machine rate$/hHourly rate for labour plus machine (for example from the machine hour rate tool).
Material per unit$Material and bought-in parts per unit.
Overhead on cost%Overhead added to the direct cost.
Margin wanted on price%Margin you want as a share of the selling price.
Price offered per unit$Price per unit the customer offers.

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Hours for the first unit
Illustration: Hours for the first unitA timeline from a start mark to an end mark; Hours for the first unit is the time between them.startendT₁Example: 10 hHours for the first unit
What it is
The hours needed to make the very first unit, from a prototype record or an estimate; the starting point of the learning curve.
Units and format
Enter a number in h: hours. The form accepts 0.000001 h to 100000 h. Required: the tool does not calculate until every input is valid.
Example
The form opens with 10 h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Every unit’s hours, and so labour cost, scale in direct proportion.
What this means: Learning rate
Illustration: Learning rateA bar of 100 parts with the share marked; Learning rate is that share out of 100. The bar follows the value you type.0 %100 %Example: 85%Learning rate
What it is
The learning rate: each time the cumulative quantity doubles, the time per unit becomes this percentage of what it was.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 50% to 100%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 85% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
A lower rate cuts the hours for later units and so lowers the unit cost.
Get it right
A lower percentage means faster learning. Base it on similar past jobs.
What this means: Units in the batch
Illustration: Units in the batchA row of identical items being counted; Units in the batch is how many there are.nExample: 50Units in the batch
What it is
The number of units in this batch. The tool counts them from the first unit ever made.
Units and format
Enter a plain number with no unit. The form accepts 1 to 100000. Use a whole number. Required: the tool does not calculate until every input is valid.
Example
The form opens with 50 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
The curve starts at unit 1, so a repeat batch is costed as if no learning carried over from earlier batches.
What this means: Set-up hours
Illustration: Set-up hoursA timeline from a start mark to an end mark; Set-up hours is the time between them.startendtExample: 6 hSet-up hours
What it is
The one-off hours to prepare for the batch, such as machine set-up, tooling and first-off inspection, charged at the same hourly rate.
Units and format
Enter a number in h: hours. The form accepts 0 h to 100000 h. Required: the tool does not calculate until every input is valid.
Example
The form opens with 6 h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Labour and machine rate
Illustration: Labour and machine rateA price tag on one unit of measure; Labour and machine rate is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $105/hLabour and machine rate
What it is
The cost of one hour of labour plus machine time, applied to both production and set-up hours.
Units and format
Enter a number in $/h: money per hour. The form accepts $0/h to $10000/h. Required: the tool does not calculate until every input is valid.
Example
The form opens with $105/h as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Material per unit
Illustration: Material per unitA price tag on one unit of measure; Material per unit is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $40Material per unit
What it is
The cost of material and bought-in parts for one unit.
Units and format
Enter a number in $: an amount of money; use one currency for every money input. The form accepts $0 to $10000000. Required: the tool does not calculate until every input is valid.
Example
The form opens with $40 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Overhead on cost
Illustration: Overhead on costA bar of 100 parts with the share marked; Overhead on cost is that share out of 100. The bar follows the value you type.0 %100 %Example: 15%Overhead on cost
What it is
Overhead added as a percentage on top of the direct labour, machine and material cost.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 0% to 200%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 15% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
What this means: Margin wanted on price
Illustration: Margin wanted on priceA bar of 100 parts with the share marked; Margin wanted on price is that share out of 100. The bar follows the value you type.0 %100 %Example: 20%Margin wanted on price
What it is
The profit you want as a percentage of the selling price; the price is unit cost ÷ (1 − margin).
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 0% to 90%. Required: the tool does not calculate until every input is valid.
Example
The form opens with 20% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Get it right
Margin on price, not markup on cost; the two give different prices for the same percentage.
What this means: Price offered per unit
Illustration: Price offered per unitA price tag on one unit of measure; Price offered per unit is the cost for each unit (per hour, per kilogram and so on).$cost foreach unitExample: $900Price offered per unit
What it is
The price per unit the customer has offered, compared with your unit cost to show the margin it gives.
Units and format
Enter a number in $: an amount of money; use one currency for every money input. The form accepts $0 to $100000000. Required: the tool does not calculate until every input is valid.
Example
The form opens with $900 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.

Method and formulas

  1. Unit time T_x = T₁ x^b with b = log₂(learning rate); cumulative hours = Σ T_x (as the learning curve tool).
  2. Cost = (cumulative + set-up) × rate + material × n, plus overhead.
  3. Price for margin m = unit cost ÷ (1 − m); margin offered = 1 − unit cost ÷ offer.
  4. Example: 50 units take 255.13 h; unit cost 676.63, price for 20% margin 845.79; the offer gives 24.819%.

Limitations

  • Unit learning curve (Crawford); the cumulative-average (Wright) model gives different numbers.
  • Learning stops at a floor set by machine time; check later units against standard times.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Quote a first production batch
  • Decide whether an offered price is acceptable
  • Show how cost falls with batch size

Who it is for

  • Estimators
  • Production managers
  • Business owners

What you get

  • Unit and cumulative hours
  • Cost in total and per unit
  • Price for the margin and the offered margin

Interpreting the result

  • The first units cost far more than the average: quote small first batches with care.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 146, 134–146. Topic reference; no source tables or recommended settings are reproduced.