BIZOMAT Tools · Operations

Capacity Check

How much can you realistically produce?

Calculates practical capacity from available hours, parallel stations, cycle time and efficiency, and compares it with demand.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Available hours / periodhrScheduled hours in the period at the constraint
Machines / parallel stationsstationsParallel machines or stations doing the same work
Cycle time / unitminMeasured cycle time per unit at the constraint
Realistic efficiency%Demonstrated efficiency (or OEE) at the constraint
Demand / periodunitsOrders or forecast for the same period

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Available hours / period
Illustration: Available hours / periodA timeline from a start mark to an end mark; Available hours / period is the time between them.startendtExample: 160 hrAvailable hours / period
What it is
The scheduled working hours of one machine or station at the constraint during the period, such as shift hours across the month.
Units and format
Enter a number in hr: hours. The form accepts 0 hr or more.
Example
The form opens with 160 hr as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Capacity rises in proportion to available hours.
Get it right
Give hours for one station; the tool multiplies by the number of stations. Deduct planned shutdowns.
What this means: Machines / parallel stations
Illustration: Machines / parallel stationsA row of identical items being counted; Machines / parallel stations is how many there are.nExample: 2 stationsMachines / parallel stations
What it is
How many identical machines or stations do the same operation side by side, so their hours add together.
Units and format
Enter a number in stations: stations. The form accepts 1 stations or more. Use a whole number.
Example
The form opens with 2 stations as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Capacity rises in proportion to the number of stations.
Get it right
Count only stations that can run this product at the same cycle time.
What this means: Cycle time / unit
Illustration: Cycle time / unitA timeline from a start mark to an end mark; Cycle time / unit is the time between them.startendtExample: 4 minCycle time / unit
What it is
The time one station takes to complete one unit at the constraint, measured from the start of one unit to the start of the next.
Units and format
Enter a number in min: minutes. The form accepts 0.01 min or more.
Example
The form opens with 4 min as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Capacity falls in proportion as cycle time grows.
Get it right
Enter minutes, not seconds: 45 seconds is 0.75 minutes.
What this means: Realistic efficiency
Illustration: Realistic efficiencyInput on the left and useful output on the right with the loss split off; Realistic efficiency is output divided by input.inputuseful outputlossηExample: 85%Realistic efficiency
What it is
The share of scheduled time that actually produces good output after breakdowns, changeovers, slow running and small stops, from recent records or OEE.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 1% to 100%.
Example
The form opens with 85% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Capacity rises in proportion to efficiency.
Get it right
Use a demonstrated figure, not a target. If changeovers are deducted from hours, do not count them here too.
What this means: Demand / period
Illustration: Demand / periodA row of identical items being counted; Demand / period is how many there are.nExample: 3500 unitsDemand / period
What it is
The number of units ordered or forecast for the same period as the available hours.
Units and format
Enter a number in units: a count of units. The form accepts 0 units or more.
Example
The form opens with 3500 units as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Utilisation rises in proportion to demand; capacity does not change.
Get it right
Match the period: monthly demand against weekly hours gives a wrong utilisation.

Method and formulas

  1. Capacity = hours × 60 × stations × efficiency ÷ cycle time (minutes)
  2. Utilisation = demand ÷ capacity
  3. Comfortable to 85%, tight to 100%

Limitations

  • Single product and constant cycle time
  • Changeovers must be inside efficiency or deducted from hours

Typical uses

  • Checking whether a forecast can be made
  • Deciding on overtime, extra shifts or outsourcing

Who it is for

  • Production planners
  • Operations managers

What you get

  • AVAILABLE, TIGHT or SHORTFALL
  • Practical capacity, utilisation and buffer

Interpreting the result

  • Utilisation above 85% leaves little room for breakdowns and variation

References

  • Hopp W. J. and Spearman M. L., Factory Physics (Waveland Press) on utilisation and variability

Learn the Concepts Behind This Tool

These BIZOMAT Library readings explain the method this tool uses, with worked examples.

BIZOMAT tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.

Open the Capacity Check calculator