Contingency Allowance

How much project contingency is reasonable?

Gives a screening contingency allowance from ratings of uncertainty, complexity and risk.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Base project cost$Base estimate before contingency
Estimate uncertainty1–5 scoreHow well defined the estimate is (1 detailed, 5 conceptual)
Complexity1–5 scoreTechnical complexity (1 routine, 5 novel)
Risk exposure1–5 scoreOverall risk exposure (1 low, 5 high)

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Base project cost
Illustration: Base project costA stack of coins and a note representing the money amount Base project cost.$Example: $100000Base project cost
What it is
The project cost estimate before any contingency is added, built up from quotations and estimates.
Units and format
Enter a number in $: an amount of money; use one currency for every money input. The form accepts $0 or more.
Example
The form opens with $100000 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
The allowance is this base multiplied by the contingency rate.
Get it right
Do not include allowances already set aside for named risks, or they are counted twice.
What this means: Estimate uncertainty
Illustration: Estimate uncertaintyA scale from the lowest to the highest score with a marker at the chosen score for Estimate uncertainty. The marker follows the slider.15lowhighExample: 3Estimate uncertainty
What it is
How well defined the estimate is, rated 1 (detailed, from firm quotations) to 5 (conceptual, early idea with little design).
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 3 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each point adds about 1.33 percentage points to the contingency rate.
Get it right
Lower this rating as design and quotations firm up at later gates.
What this means: Complexity
Illustration: ComplexityA scale from the lowest to the highest score with a marker at the chosen score for Complexity. The marker follows the slider.15lowhighExample: 3Complexity
What it is
How technically difficult the work is, rated 1 (routine) to 5 (novel or untried), used as one of the three contingency drivers.
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 3 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each point adds about 1.33 percentage points to the contingency rate.
Get it right
Rate the technical challenge of the work, not the overall size of the project.
What this means: Risk exposure
Illustration: Risk exposureA scale from the lowest to the highest score with a marker at the chosen score for Risk exposure. The marker follows the slider.15lowhighExample: 3Risk exposure
What it is
The overall exposure to things that could go wrong, such as site conditions, supply or approvals, rated 1 (low) to 5 (high).
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 3 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each point adds about 1.33 percentage points to the contingency rate.
Get it right
Base it on the project risk register so the rating can be explained.

Method and formulas

  1. Combined rating p = (uncertainty + complexity + risk) ÷ 15
  2. Rate = 5% + 20% × p
  3. Allowance = base × rate

Limitations

  • A screening heuristic, not a quantified risk analysis
  • Does not replace your estimating standard

Typical uses

  • Early estimates and budget requests
  • Sense-checking a contingency proposed by others

Who it is for

  • Estimators
  • Project managers

What you get

  • Contingency rate (9–25%) and allowance
  • Total including contingency

Interpreting the result

  • For large or poorly defined projects, use range estimating or Monte Carlo analysis
  • Do not double-count risks already priced in the base estimate

References

  • AACE International Recommended Practice 40R-08, Contingency Estimating — General Principles

Learn the Concepts Behind This Tool

These BIZOMAT Library readings explain the method this tool uses, with worked examples.