BIZOMAT Tools · Projects

Project Health Check

How healthy is this project right now?

Combines schedule and cost variance with scope, risk and resource ratings into a project health score, and points to the weakest area.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Schedule variance%Schedule variance % from the baseline schedule or earned value (positive = behind)
Cost variance%Cost variance % against the approved budget (positive = over)
Scope stability1–5 scoreRating of scope stability from the change log (1 unstable, 5 stable)
Risk exposure1–5 scoreRating from the risk register (1 low, 5 very high)
Resource adequacy1–5 scoreRating of resource adequacy (1 inadequate, 5 adequate)

What each input means

Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.

What this means: Schedule variance
Illustration: Schedule varianceA bar of 100 parts with the share marked; Schedule variance is that share out of 100. The bar follows the value you type.0 %100 %Example: 5%Schedule variance
What it is
How far the project is behind or ahead of its baseline schedule, as a percentage. Positive means behind plan, negative means ahead.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts -100% to 100%.
Example
The form opens with 5% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each 1 % behind removes 2 points from the schedule signal; above 10 % flags REVIEW and above 20 % FAIL.
Get it right
Watch the sign: a project 10 % behind is entered as 10, not −10. Being ahead earns no extra points.
What this means: Cost variance
Illustration: Cost varianceA bar of 100 parts with the share marked; Cost variance is that share out of 100. The bar follows the value you type.0 %100 %Example: 3%Cost variance
What it is
How far forecast or actual cost is over or under the approved budget, as a percentage. Positive means over budget, negative means under.
Units and format
Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts -100% to 100%.
Example
The form opens with 3% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each 1 % over budget removes 2 points from the cost signal; above 10 % flags REVIEW and above 20 % FAIL.
Get it right
Use controlled figures, such as earned value or the latest cost report, not an estimate from memory.
What this means: Scope stability
Illustration: Scope stabilityA scale from the lowest to the highest score with a marker at the chosen score for Scope stability. The marker follows the slider.15lowhighExample: 4Scope stability
What it is
How settled the project scope is, judged from the change log, rated 1 (constantly changing) to 5 (stable and agreed).
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 4 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each point adds 4 points to the health score; 2 or less raises a warning.
Get it right
Base it on the number and size of recent change requests, not on how the team feels.
What this means: Risk exposure
Illustration: Risk exposureA scale from the lowest to the highest score with a marker at the chosen score for Risk exposure. The marker follows the slider.15lowhighExample: 3Risk exposure
What it is
The overall level of open risk on the project, from the risk register, rated 1 (low) to 5 (very high). A higher rating means more exposure.
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 3 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each step up removes 4 points from the health score.
Get it right
The scale runs the other way from the others: a 5 here is bad.
What this means: Resource adequacy
Illustration: Resource adequacyA scale from the lowest to the highest score with a marker at the chosen score for Resource adequacy. The marker follows the slider.15lowhighExample: 4Resource adequacy
What it is
Whether the project has the people, skills and equipment it needs right now, rated 1 (inadequate) to 5 (adequate).
Units and format
Move the slider to a score from 1 (low) to 5 (high).
Example
The form opens with 4 as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
Effect on the result
Each point adds 4 points to the health score; 2 or less raises a warning.
Get it right
Count only people actually available to the project, not those named on the plan but busy elsewhere.

Method and formulas

  1. Schedule and cost signals = 100 − 2 × positive variance % (minimum 0)
  2. Score = 0.2 × schedule + 0.2 × cost + 20 × scope ÷ 5 + 20 × (6 − risk) ÷ 5 + 20 × resources ÷ 5
  3. Variance REVIEW above 10%, FAIL above 20%

Limitations

  • Favourable variances are not rewarded
  • Fixed weights
  • Ratings are subjective

Typical uses

  • Monthly project reporting
  • Portfolio reviews
  • Deciding where to focus a recovery

Who it is for

  • Project managers
  • Sponsors and PMOs

What you get

  • HEALTHY, AT RISK or CRITICAL
  • Health score and weakest area
  • Variance checks

Interpreting the result

  • Act on the weakest area first
  • Track the score over several periods; the trend matters more than one value

References

  • PMI, Practice Standard for Earned Value Management

BIZOMAT tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.